TIRUMALA TIRUPATI DEVASTHANAMS, TIRUPATI
CHITTOOR (DIST) ANDHRAPRADESH
SUPERINTENDING ENGINEER-II
Adv.
No. 08/TA/ SE-II/ TTD/ TPT/ 2010-11 Date: 21 .07 .2010
‘e’-PROCUREMENT TENDER NOTICE
|
Sl. No. |
NIT. No. |
Name of work |
Estimate Amount Rs. In lakhs & Time for completion |
Schedule down load start date |
Down load end date & last
date for bid submission |
|
I |
SUPERINTENDING |
||||
|
1 |
59/SE-II/TTD /2010-11 |
Improvements to the SMC Cottages (Group-II) from
222 to 225, 227 to and 238 to 244 at Tirumala. |
62.00 3 Months |
13.08.2010 5:00 PM |
28.08..2010 1:00 PM & 28.08.2010 3:00 PM |
|
2 |
60/SE-II/TTD /2010-11 |
Improvements
to the SMC Cottages (Group-III) from 245 to 260, 262 to 265 and 273 to 276 at
Tirumala. |
70.00 3 Months |
13.08.2010 5:00 PM |
28.08..2010 1:00 PM & 28.08.2010 3:00 PM |
|
3 |
61/SE-II/TTD/2010-11 |
Improvements to the Cottages in HVC Area
Group-II (Block no. 637, 639, 641,
642, 643, 645, 647, 681, 683, 685 & 687 with 88 Rooms) at Tirumala. |
81.00 3 Months |
13.08.2010 5:00 PM |
28.08..2010 1:00 PM & 28.08.2010 3:00 PM |
|
4 |
62/ SE-II/TTD/2010-11 |
Improvements to the Cottages in HVC Area Group-IV
(Block no. 674, 676, 678, 680, 682, 684, 690, 691, 692, 693 & 694 with 88
Rooms) at Tirumala |
81.00 3 Months |
17.08.2010 5:00 PM |
01.09..2010 1:00 PM & 01.09.2010 3:00 PM |
|
5 |
63/ SE-II/TTD/2010-11 |
Improvements to the HVDC area Cottages No. 491,
492, 493, 494 & 496 at Tirumala. |
48.00 3 Months |
17.08.2010 5:00 PM |
01.09..2010 1:00 PM & 01.09.2010 3:00 PM |
|
6 |
64/ SE-II/TTD/2010-11 |
Improvements to the cottages in HVC Area
Group-III (Block No. 644, 646, 648, 671, 673, 675, 677, 679, 686, 688 &
689 with 88 Rooms) at Tirumala |
81.00 3 Months |
17.08.2010 5:00 PM |
01.09..2010 1:00 PM & 01.09.2010 3:00 PM |
|
7 |
65/SE-II/TTD/2010-11 |
Construction
of New Kitchen Block at VQC-II at Tirumala. |
270.00 9 Months |
05.08.2010 5:00 PM |
21.08..2010 1:00 PM & 21.08.2010 3:00 PM |
|
8 |
66/SE-II/TTD/2010-11 |
Providing
cordon Security around Sri T.T.,&
Mada streets at Tirumala. |
295.00 9 Months |
10.08.2010 5:00 PM |
26.08..2010 1:00 PM & 26.08.2010 3:00 PM |
|
9 |
67/SE-II/TTD /2010-11 |
Construction
of RCC Roof Shelters in place of damaged Iron shelter from Step No.
2910 to 3332 in Alipiri footpath
Tirumala. |
94.00 9 Months |
05.08.2010 5:00 PM |
21.08..2010 1:00 PM & 21.08.2010 3:00 PM |
|
10 |
68/SE-II/TTD /2010-11 |
Widening of existing single lane road
to two lane road from Vedagiri Junction to Srivari Padalu at Tirumala |
210.00 9 Months |
10.08.2010 5:00 PM |
26.08..2010 1:00 PM & 26.08.2010 3:00 PM |
|
11 |
69/SE-II/TTD /2010-11 |
Widening of footpath and providing
shelter from Sri Lakshmi Narasimha Swamy temple to Mokalimitta (Left over
portions) in 1st Ghat road, Tirumala |
235.00 9 Months |
05.08.2010 5:00 PM |
21.08..2010 1:00 PM & 21.08.2010 3:00 PM |
|
12 |
70/SE-II/TTD /2010-11 |
Construction of RCC Kerb walls from
12/0 to 16/7 KM in 2nd Ghat road, Tirumala |
15.00 2 Months |
10.08.2010 5:00 PM |
26.08..2010 1:00 PM & 26.08.2010 3:00 PM |
|
13 |
71/SE-II/TTD /2010-11 |
Construction of Mini Kalyanakatta
adjacent to SPGH Sub-Enquiry and Improvements to SPGH Sub-Enquiry Office in
SP Nagar area Tirumala |
17.00 2 Months |
11.08.2010 5:00 PM |
27.08..2010 1:00 PM & 27.08.2010 3:00 PM |
|
II |
EXECUTIVE ENGINEER-V Division (SHORT TENDER) |
||||
|
1 |
4/EE-V/TTD/2010-11 |
Erection and removal of decorative ply-wood
arches at various places, Tirumala in
connection with Srivari Salakatla & Navarathri Brahmotsavams for the year
2010 |
1.85 |
05.08.2010 5:00 PM |
13.08..2010 1:00 PM & 13.08.2010 3:00 PM |
III |
EXECUTIVE
ENGINEER-WW Division (SHORT TENDERS) |
||||
|
1 |
82 /
EEWW / 2010-11 |
Annual
maintenance Contract and Materials required for gas leakage alarm system for
Srivari potu LPG plant and Annadanam Canteen at Tirumala for the year 2010-11
|
1.50 12
Months |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
2 |
83 /
EEWW / 2010-11 |
Annual
maintenance of Weighing machines and Load cells Sri TT, SVNACC and marketing
Godown at Tirumala for the year 2010-11 |
1.50 12
Months |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
3 |
84 /
EEWW / 2010-11 |
Annual
maintenance and supply of Spares for Currency counting machines in Srivari
parakamani in Sri TT at Tirumala for the year 2010-11 |
0.70 12
Months |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
4 |
85 /
EEWW / 2010-11 |
Supply
of SS Supports (Channels) to trolley brackets in SVNACC & PAC-II at
Tirumala |
0.80 15
days |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
5 |
86 /
EEWW / 2010-11 |
Providing
Cold water connections to Solar Hot water Systems at Kousthubham Guest house
at Tirumala |
1.45 15
days |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
6 |
87 /
EEWW / 2010-11 |
Supply
of Stand-by Motor to the Machines in temple section of Dy.EE, Mechanical
Sub-division, Tirumala
|
4.00 1
Month |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
7 |
88 /
EEWW / 2010-11 |
Supply
of Trolleys, Castro wheels to SVNAC and PAC –II at Tirumala |
4.90 1
Month |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
8 |
89 /
EEWW / 2010-11 |
Supply,
Installation and Commissioning of Stand-by Jockey pump to the fire fighting
system at BSM plant for Sri T.T. Tirumala
|
1.30 1
Month |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
9 |
90 /
EEWW / 2010-11 |
Laying
of 100 mm dia DI pipe line to New Annadanam Sump & Kalyanamasthu building
at VSGH Sump to New Annadanam complex at Tirumala |
10.00 2
Months |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
10 |
91 /
EEWW / 2010-11 |
Providing
Drinking water facilities alround outer ends of galleries in FOUR Mada
Streets and front side of open yard of Srivari temple, Tirumala |
9.00 1
Month |
26-07-2010 5:00 PM |
03.08..2010 1:00 PM & 03.08.2010 3:00 PM |
|
I V |
EXECUTIVE ENGINEER-FMS Division |
||||
|
1 |
08/EEFMS/2010-11 |
Construction of Sentry post and Security Check
point at S.P.Guest hosue, tirumala |
2.10 1 Month |
03.08.2010 5:00 PM |
18.08..2010 1:00 PM & 18.08.2010 3:00 PM |
Note:- For full details log on to the website https://tender.eprocurement.gov.in/
or
http://www.eprocurement.gov.in/
In the service of Lord Venkateswara
Sd/-M.Ramesh Reddy
Superintending Engineer-II